What electrics does a garden-room golf simulator need?

Tom Hayward Tom Hayward, founder of OpenGolfer · Last reviewed · 4 min read

The short answer

Usually a new circuit from the house, run underground in armoured cable, with 30mA RCD-protected sockets by the projector, PC and mat. In England a new circuit is notifiable under Part P, even in a small exempt outbuilding, so use a registered electrician who certifies it. This is guidance, not legal advice.

In summary

A garden-room simulator needs a proper supply from the house: usually a new circuit, run underground in armoured cable, with RCD-protected sockets in the room. In England a new circuit is notifiable building work under Part P, so use an electrician registered with a competent person scheme, who certifies it for you. This page explains what to ask for. It isn't legal or electrical advice, and the design is your electrician's job.

What the simulator needs

The simulator itself is modest: a projector, a PC or the Garmin R50, the launch monitor's charger, and perhaps speakers and lighting. In a garden room the bigger loads are heating and a dehumidifier. A fan heater is typically 2kW to 3kW on its label, which is most of what one 13A socket can supply. Tell the electrician everything you plan to plug in, heater included, so they can size the circuit.

Plan the sockets with the layout. Most rooms want one near the projector, one by the PC and one at the hitting position, plus one for a heater or dehumidifier. Uneekor says that if its adapter doesn't fit the outlet, you should have a proper socket fitted by a qualified electrician, which is a fair rule for all the kit. The cabling guide covers where the leads go.

The rules: Part P in England

Part P of the Building Regulations covers electrical safety in homes. The government's Approved Document P says it applies to installations "in outbuildings such as sheds, detached garages and domestic greenhouses", and in gardens, where the electricity comes from the house.

Small outbuildings are often exempt from Building Regulations. The Planning Portal says they won't normally apply under 15 square metres, or between 15 and 30 square metres if there's no sleeping accommodation and the building is at least a metre from the boundary or built substantially of non-combustible materials. But Approved Document P is clear that garages and sheds that share their electricity with a dwelling "are not exempt from Part P" and must comply.

What is notifiable

Notifiable means building control must be told. In England that's:

  • the installation of a new circuit;
  • the replacement of a consumer unit (the fuse box);
  • any addition or alteration to existing circuits in a special location, meaning near a bath or shower, or a room with a swimming pool or sauna heater.

A new circuit from your house consumer unit to the garden room is therefore notifiable. Approved Document P gives a close example: connecting a garage door to an existing isolator isn't notifiable, but installing a new circuit to that isolator is. Work that isn't notifiable must still be designed, installed, tested and certificated to BS 7671, the UK wiring regulations.

How notification works

Approved Document P gives three routes:

  1. A registered competent person, meaning an electrician in a government-authorised scheme, self-certifies the work. This is the usual route.
  2. A registered third-party certifier inspects and certifies it.
  3. You or your installer tell building control before work starts, and they inspect it.

With a registered electrician, you should get a BS 7671 Electrical Installation Certificate for the job, and a Building Regulations compliance certificate. Gov.uk says the competent person scheme certificate comes within 8 weeks of completion. Keep both: you'll be asked for them when you sell the house. Find a registered electrician on the Electrical Competent Person Register, which gov.uk links to.

Wales, Scotland and Northern Ireland

  • Wales has its own Part P, which is wider: outdoor work is notifiable even without a new circuit.
  • Scotland has no Part P. Work comes under the building standards system, through an approved certifier or the local authority.
  • Northern Ireland has no statutory requirements for domestic electrical work, according to Electrical Safety First. A registered electrician and a BS 7671 certificate are still the safe way to do it.

The supply: what to ask the electrician about

  • A dedicated circuit. Usually from the house consumer unit, often feeding a small consumer unit in the garden room with its own sockets and lighting circuits.
  • Buried armoured cable. The wiring regulations want a buried cable to have earthed armour or a metal sheath, or to run in a conduit or duct that protects it as well. Steel wire armoured (SWA) cable is the usual choice. The IET recommends at least 0.5m deep, and 1.0m in cultivated ground, with warning tape or cable covers above it. Ask for the route to be drawn on the certificate so nobody digs into it later.
  • RCD protection. An RCD (residual current device) cuts the power in a fraction of a second if current leaks to earth, for example through a person. BS 7671 calls for 30mA RCD protection on socket-outlets rated up to 32A, and Electrical Safety First says to use an RCD with all outdoor electrical equipment.
  • Cable size. Over a long garden run the voltage drops, so the electrician may specify a thicker cable than the load alone suggests. That calculation is theirs.
  • Data. If the Wi-Fi won't reach, ask whether a network cable can go in the same trench, in its own duct.

BS 7671 was updated in April 2026 (Amendment 4), and the older editions are withdrawn on 15 October 2026, so your electrician will be working to the current edition.

What not to do

  • Don't run a permanent supply on an extension lead or cable reel down the garden. Electrical Safety First says outdoor leads must be weather-resistant and used with an RCD. A lead is a temporary fix, not a supply for a room you'll use all year.
  • Don't plug one extension lead into another.
  • Don't do the new circuit yourself unless you notify building control first and have it inspected.

Garden-room electrics checklist

From Approved Document P, gov.uk, the Planning Portal, the IET and Electrical Safety First, checked 6 October 2026
ItemWhat the source saysSource
Does Part P apply to an outbuilding?Yes, where it shares its electricity with the house, even if exempt from other Building RegulationsApproved Document P, para 2.3
Notifiable work (England)A new circuit; a new consumer unit; additions or alterations in a special locationApproved Document P, para 2.5
Not notifiableOther additions and alterations, replacements, repairs; still to BS 7671Approved Document P, paras 2.7 and 3.13
Routes to complyRegistered competent person; third-party certifier; building controlApproved Document P, para 3.1
PaperworkBS 7671 Electrical Installation Certificate and Building Regulations compliance certificateApproved Document P, paras 3.3 to 3.4
Outbuilding exemptionUnder 15m2, or 15 to 30m2 with conditions, with no sleeping accommodationPlanning Portal
Buried cableEarthed armour or metal sheath, or protective duct; 0.5m deep recommended, 1.0m in cultivated ground; marked with tape or coversIET Wiring Matters
RCD30mA RCD on socket-outlets up to 32A; an RCD with all outdoor equipmentIET; Electrical Safety First
WalesOutdoor work notifiable even without a new circuitWelsh Government
Scotland / Northern IrelandBuilding standards system / no statutory requirementElectrical Safety First

Guidance only, not legal or electrical advice. Your electrician designs the installation to the current BS 7671 (2018 + A4:2026).

Best practice

  1. Use a registered electricianFind one on the Electrical Competent Person Register. They notify building control for you and issue the certificates.
  2. Give them the full loadList the projector, PC, chargers, lighting, heater and dehumidifier. The heater decides the circuit, not the simulator.
  3. Plan sockets with the layoutOne by the projector, one by the PC, one at the mat and one for heating, decided before the room is lined.
  4. Get the cable route recordedElectrical Safety First strongly recommends drawing the buried cable route on the installation certificate. Keep it with the house papers.
  5. Duct the data cableIf Wi-Fi won't reach, ask for a network cable in its own duct in the same trench.

Gotchas to avoid

  • Exempt building, not exempt electricsA small outbuilding may need no Building Regulations approval, but Approved Document P says its electrics must still comply with Part P.
  • Extension lead down the gardenElectrical Safety First says outdoor leads must be weather-resistant and used with an RCD. Even then, a lead is a temporary fix, not a permanent supply.
  • Missing certificates at saleWithout an installation certificate and compliance certificate, a buyer's solicitor will ask questions. Keep both.
  • Long runs and voltage dropA long garden run may need thicker cable than the load suggests. Leave the sizing to the electrician.

Our recommendation

Have a registered electrician install a dedicated, RCD-protected circuit in buried armoured cable, and keep both certificates.

If you're in England and need a new circuit
A registered competent person self-certifies it and notifies building control.
If your electrician isn't registered
Tell building control before work starts, and they'll inspect it.
If you're in Wales
Outdoor work is notifiable even without a new circuit; use a registered electrician.
If the room will have a heater
Tell the electrician its rating so the circuit is sized for it.

Fewer plugs, tidier room

Free Sim Design Concierge

Your simulator, designed with Tom

A bespoke consultation with a 3D CAD design of your room and the options I'd recommend for it.

Send your room size or a photoYour room in 3D CADRecommended options, live pricesFree, no obligation

Tom Hayward, founder · usually replies within the hour, 8am–8pm

Questions people ask

Do I need building regulations for a garden room simulator?

The building may not, if it's under 15 square metres, or 15 to 30 with conditions, and has no sleeping accommodation. The electrics are different: Approved Document P says outbuildings sharing the house's electricity must comply with Part P.

Is a new circuit to the garden room notifiable?

Yes, in England. Approved Document P lists a new circuit as notifiable. A registered electrician self-certifies it and notifies building control for you.

Can I use an extension lead from the house?

Only for temporary use. Electrical Safety First says outdoor leads must be weather-resistant and used with an RCD. For a room you'll use all year, have a proper supply installed.

What certificates should I get?

A BS 7671 Electrical Installation Certificate, and a Building Regulations compliance certificate from the competent person scheme. Gov.uk says the scheme certificate comes within 8 weeks of completion.

How deep does the cable need to be?

The IET recommends at least 0.5m to avoid damage from general gardening, and 1.0m in cultivated ground, with warning tape or covers above. The cable needs earthed armour or a protective duct. Your electrician decides.

Is this legal advice?

No. It's a plain-English summary of the official guidance to help you brief an electrician. They design the installation and are responsible for it.